Engineering Management Old Question Practice

By admin

Updated on:

Follow Us
60+ Old Questions of Engineering Management
-- Advestisement --
0%
0 votes, 0 avg
2
Created on

Civil Sub Engineering

Engineering Management Old Question Practice

Fill Your Details

1 / 50

1. Types of organizations used in construction industry is

2 / 50

2. For the procurement of works, what is the maximum estimates amount for which a tender notice is not mandatory ?

3 / 50

3. Contractor’s profit and overhead is

4 / 50

4. Which types of networks was first develops for planning of any project

5 / 50

5. The dispute in construction is resolved through discussion of all parties on their respective stands leading to the consensus. The process is called

6 / 50

6. The role of consultant is to

7 / 50

7. The dummy activity in CPM

8 / 50

8. Which of the following types of selection is adopted broadly in Nepal for the procurement for services ?

9 / 50

9. Which method is known as minimum cost or maximum times schedule method

10 / 50

10. What is the maximum overhead added to the rate analysis?

11 / 50

11. What are the key dates of a standard contracting procedure of a project?

12 / 50

12. Contractor tax

13 / 50

13. Tender does not contain

14 / 50

14. Tender guarantee is generally

15 / 50

15. Responsibility of overseer is to

16 / 50

16. A construction schedule is prepared after collecting

17 / 50

17. Construction schedule is prepared after collecting

18 / 50

18. A contract is

19 / 50

19. The authority to approve a variation order of an amount exceeding Rs 5 but less than 15% of contract amount is

20 / 50

20. Contractor profile is added for

21 / 50

21. The technology and or software used for project planning includes all but

22 / 50

22. Most of the works related to measurement of items and making entry to the measurement book is initiated by

23 / 50

23. The time b which a particular activity may be delayed without affecting the proceeding and succeeding activities is known as

24 / 50

24. Various activities of a project, are shown on bar charts by:

25 / 50

25. Petty contract is:

26 / 50

26. Necessary elements of the estimate are

27 / 50

27. The amount of publish for tends in national paper is

28 / 50

28. PERT analysis is based on

29 / 50

29. It means offerings, giving, receiving, or soliciting directly or indirectly, anything of value of influencing improperly the action of another party

30 / 50

30. Most frequently used method of organizing labour for a construction project is based on

31 / 50

31. A muster roll is

32 / 50

32. The completion report includes

33 / 50

33. Which technique was used firstly for the planning of a project

34 / 50

34. The tender is

35 / 50

35. As per the prevailing regulation (PRR) in Nepal, what is the % of the price escalation contingency to be provided at the end of the earth estimate preparation ?

36 / 50

36. Performance security is necessary

37 / 50

37. The CPM stands for

38 / 50

38. Code used in Nepal for building construction/design is

39 / 50

39. Reasons for cost and time-extension in any project are

40 / 50

40. A contractors can start the construction works following the receipts of

41 / 50

41. In critical path method (CPM), the actual performance of task is called

42 / 50

42. The first stage of a construction is

43 / 50

43. Work charge establishment.

44 / 50

44. Commonly adopted method if planning the construction activities and labour in a project to optimize the construction period is

45 / 50

45. Muster rolls are used for

46 / 50

46. Line of balance technique used for

47 / 50

47. Which of the following in not a basic requirements for quality control method adapted in a project?

48 / 50

48. A slack of head event and different between total float and free float is

49 / 50

49. The term CPM in construction management is an abbreviation of

50 / 50

50. The difference between the time available to do the job and time required to do the job is known

The average score is 39%