Nepal’s No #1 Platform For PSC Competitors

Join us on Telegram

Join Now

Join us on Whatsapp

Join Now
Home
Home
Home
Home
Home » Exam » Engineering Management Old Question Practice
-- Advestisement --
Home » Exam » Engineering Management Old Question Practice

Engineering Management Old Question Practice

By admin

Updated on:

Follow Us
60+ Old Questions of Engineering Management
-- Advestisement --
0%
0 votes, 0 avg
2
Created on

Civil Sub Engineering

Engineering Management Old Question Practice

Fill Your Details

1 / 50

1. The technology and or software used for project planning includes all but

2 / 50

2. The difference between the time available to do the job and time required to do the job is known

3 / 50

3. Which technique was used firstly for the planning of a project

4 / 50

4. A muster roll is

5 / 50

5. Commonly adopted method if planning the construction activities and labour in a project to optimize the construction period is

6 / 50

6. Code used in Nepal for building construction/design is

7 / 50

7. The dispute in construction is resolved through discussion of all parties on their respective stands leading to the consensus. The process is called

8 / 50

8. Construction schedule is prepared after collecting

9 / 50

9. As per the prevailing regulation (PRR) in Nepal, what is the % of the price escalation contingency to be provided at the end of the earth estimate preparation ?

10 / 50

10. Work charge establishment.

11 / 50

11. Tender does not contain

12 / 50

12. Necessary elements of the estimate are

13 / 50

13. It means offerings, giving, receiving, or soliciting directly or indirectly, anything of value of influencing improperly the action of another party

14 / 50

14. The authority to approve a variation order of an amount exceeding Rs 5 but less than 15% of contract amount is

15 / 50

15. Most frequently used method of organizing labour for a construction project is based on

16 / 50

16. The amount of publish for tends in national paper is

17 / 50

17. Contractor’s profit and overhead is

18 / 50

18. Most of the works related to measurement of items and making entry to the measurement book is initiated by

19 / 50

19. Contractor tax

20 / 50

20. Contractor profile is added for

21 / 50

21. Petty contract is:

22 / 50

22. Performance security is necessary

23 / 50

23. Tender guarantee is generally

24 / 50

24. Muster rolls are used for

25 / 50

25. A slack of head event and different between total float and free float is

26 / 50

26. Which types of networks was first develops for planning of any project

27 / 50

27. Which of the following in not a basic requirements for quality control method adapted in a project?

28 / 50

28. What is the maximum overhead added to the rate analysis?

29 / 50

29. The CPM stands for

30 / 50

30. In critical path method (CPM), the actual performance of task is called

31 / 50

31. PERT analysis is based on

32 / 50

32. A construction schedule is prepared after collecting

33 / 50

33. The role of consultant is to

34 / 50

34. The term CPM in construction management is an abbreviation of

35 / 50

35. The tender is

36 / 50

36. The completion report includes

37 / 50

37. Which method is known as minimum cost or maximum times schedule method

38 / 50

38. A contract is

39 / 50

39. The first stage of a construction is

40 / 50

40. The dummy activity in CPM

41 / 50

41. Line of balance technique used for

42 / 50

42. Various activities of a project, are shown on bar charts by:

43 / 50

43. Which of the following types of selection is adopted broadly in Nepal for the procurement for services ?

44 / 50

44. The time b which a particular activity may be delayed without affecting the proceeding and succeeding activities is known as

45 / 50

45. For the procurement of works, what is the maximum estimates amount for which a tender notice is not mandatory ?

46 / 50

46. A contractors can start the construction works following the receipts of

47 / 50

47. Reasons for cost and time-extension in any project are

48 / 50

48. Types of organizations used in construction industry is

49 / 50

49. Responsibility of overseer is to

50 / 50

50. What are the key dates of a standard contracting procedure of a project?

The average score is 39%

0%

Exit

-- Advestisement --

Leave a Comment