-- Advestisement --Home » Exam » Engineering Management Old Question Practice ExamEngineering Management Old Question PracticeBy adminUpdated on: May 17, 2024Follow Us -- Advestisement --0% 0 votes, 0 avg 2 Created on May 06, 2024Civil Sub EngineeringEngineering Management Old Question Practice Fill Your Details 1 / 501. The technology and or software used for project planning includes all but A. Primavera B. Ms project C. CPM D. Arc GIS 2 / 502. The difference between the time available to do the job and time required to do the job is known A. Event B. Float C. Duration D. Constraint 3 / 503. Which technique was used firstly for the planning of a project A. Bar chart B. CPM C. PERT D. Milestone 4 / 504. A muster roll is A. Attendance sheet of temporary workers for remunerating B. Inventory list of equipment and list of people on the site C. List of jobs the workers must do on site D. Several drawing sheets of a site rolled in a bundle 5 / 505. Commonly adopted method if planning the construction activities and labour in a project to optimize the construction period is A. Calendar plan B. Critical path method C. Entry of labour and equipment D. Construction schedule 6 / 506. Code used in Nepal for building construction/design is A. National Building Codes (NBC) B. Indian Standard Codes (ISC) C. American Standard Codes (ASC) D. British Standard Codes (BSC) 7 / 507. The dispute in construction is resolved through discussion of all parties on their respective stands leading to the consensus. The process is called A. Amicable settlement B. Arbitration C. Dispute resolution board D. Dispute adjudication board 8 / 508. Construction schedule is prepared after collecting A. Number of operation B. Output of labour C. Output of machinery D. All of the above 9 / 509. As per the prevailing regulation (PRR) in Nepal, what is the % of the price escalation contingency to be provided at the end of the earth estimate preparation ? A. None B. 5% C. 0% D. 20% 10 / 5010. Work charge establishment. A. 1.5 % B. 2.5 % C. 3.5 % D. 5 % 11 / 5011. Tender does not contain A. Notice B. Item of work C. Estimated cost D. Item rate 12 / 5012. Necessary elements of the estimate are A. Drawing B. Rates C. Specification D. All of the above 13 / 5013. It means offerings, giving, receiving, or soliciting directly or indirectly, anything of value of influencing improperly the action of another party A. Corrupt practice B. Fraudulent practice C. Coercive practice D. Collusive practice 14 / 5014. The authority to approve a variation order of an amount exceeding Rs 5 but less than 15% of contract amount is A. Chief of local division B. Chief of the department C. Secretary of concerned ministry D. Council of ministers 15 / 5015. Most frequently used method of organizing labour for a construction project is based on A. Calender plan B. Bar chart C. Pie chart D. CPM analysis 16 / 5016. The amount of publish for tends in national paper is A. > 1.5 lakh B. >3 lakh C. >10 lack D. > 20 lakh 17 / 5017. Contractor’s profit and overhead is A. 10 % B. 15 % C. 20 % D. All of the above 18 / 5018. Most of the works related to measurement of items and making entry to the measurement book is initiated by A. Site supervisor B. Site engineer C. Resident engineer D. Project in charge 19 / 5019. Contractor tax A. 1.5 % B. 2.5 % C. 5 % D. 10 % 20 / 5020. Contractor profile is added for A. Detailed estimate B. Rate analysis C. Valuation D. Salvage 21 / 5021. Petty contract is: A. Work entreated to a contractor without any restrictions B. Contract wholly owned a single staff C. Contract selected as the best one D. A contract of small and volume to be fully handled by a staff 22 / 5022. Performance security is necessary A. After construct agreement to the successful bidder B. Before bid opening to all bidders C. During bid opening to all bidders D. Before contract agreement to the successful bidder. 23 / 5023. Tender guarantee is generally A. 1 % of contract amount B. 2.5% of contract amount C. 5% of contract amount D. None of the above 24 / 5024. Muster rolls are used for A. To pay wages of workers employed on daily basis B. To record the daily construction activities C. To evaluate the construction activities D. To evaluate the performance of workers 25 / 5025. A slack of head event and different between total float and free float is A. Free float B. Latest float C. Interfering float D. Earlier float 26 / 5026. Which types of networks was first develops for planning of any project A. PERT B. CPM C. Milestone D. Bar chart 27 / 5027. Which of the following in not a basic requirements for quality control method adapted in a project? A. Materials schedule B. Sampling path method C. Entry labour and equipment D. None of above 28 / 5028. What is the maximum overhead added to the rate analysis? A. 5 % B. 50 % C. 15 % D. 20 % 29 / 5029. The CPM stands for A. Critical path method B. Computer programing mode C. Critical path method D. Controlling, planning, and maintenance 30 / 5030. In critical path method (CPM), the actual performance of task is called A. An event B. An activity C. A duration D. Critical task 31 / 5031. PERT analysis is based on A. Optimistic time B. Pessimistic time C. Most likely time D. All of the above 32 / 5032. A construction schedule is prepared after collecting A. Number of operations B. Outputs of labour C. Quality of various items D. All of the above 33 / 5033. The role of consultant is to A. Design B. Midrate C. Supervision D. All of the above 34 / 5034. The term CPM in construction management is an abbreviation of A. Construction project management B. Construction path method C. Critical path method D. Critical project management 35 / 5035. The tender is A. Notice inviting bids B. Written offer submitted by contractor to execute work C. An agreement enforceable by law D. None of these 36 / 5036. The completion report includes A. The details of the fund bill paid to the contractor B. The details of the all bills paid to the contractor C. The details of all the bills, variation along with as built drawing D. The completion of all the documents during project implementation 37 / 5037. Which method is known as minimum cost or maximum times schedule method A. PERT B. CPM C. Bar chart D. All of the above 38 / 5038. A contract is A. A bargain between two parties B. A risk of the contractor C. A money given to the contractor. D. An agreement to do something especially one that is contactable by law 39 / 5039. The first stage of a construction is A. Initiation of proposal B. Allocation of fund C. Preparation of tender D. Acceptance of tender and agreement 40 / 5040. The dummy activity in CPM A. Has no tail event but only a head event B. Has only head event C. Does not required any resources or any time D. Has no bearing and the network and appear anywhere. 41 / 5041. Line of balance technique used for A. Planning of any project B. Planning of any activity C. Planning an event D. Comprising actual progress with the schedule program 42 / 5042. Various activities of a project, are shown on bar charts by: A. Vertical lines B. Horizontal lines C. Dost D. Crosses 43 / 5043. Which of the following types of selection is adopted broadly in Nepal for the procurement for services ? A. Quality based B. Cost based C. Cost and quality based D. Technology based 44 / 5044. The time b which a particular activity may be delayed without affecting the proceeding and succeeding activities is known as A. Total float B. Free float C. Interfering float D. Independent float 45 / 5045. For the procurement of works, what is the maximum estimates amount for which a tender notice is not mandatory ? A. Rs. 1 crore B. 50 lakhs C. Rs. 20 lakhs D. Rs. 5 lakhs 46 / 5046. A contractors can start the construction works following the receipts of A. Award of construct B. Contract agreement C. Notice of proceed D. Variation order 47 / 5047. Reasons for cost and time-extension in any project are A. Omission of items B. Change in design C. Improper rate D. All of the above 48 / 5048. Types of organizations used in construction industry is A. Effective organization B. Line organization C. Line staff organization D. In functional organization 49 / 5049. Responsibility of overseer is to A. Maximize the BOQ B. Minimize the BOQ C. Optimize the BOQ D. None of these 50 / 5050. What are the key dates of a standard contracting procedure of a project? A. Call for bidding and contract award B. Call for bidding and submission; bid evaluation C. Call for bidding, bid submission bid evaluation and contract award D. Call for bidding, bid submission, and contract award The average score is 39% 0% Restart quiz Exit -- Advestisement --