Steel rebar estimate for project is done based on
(a) running meter (b) MT (c) square meter (d) cubic meter Ans :- (b) MT Explanation :- Steel rebar work ...
In the detailed estimate the volumes are worked out to the nearest
OR Accuracy in the measurement of the volume in cubic meter should be near to (a) 0.00001 cum (c) 0.001 ...
The unit of measurement in the estimation for reinforcement of RCC work is
(a) cubic meter (b) quintal (c) kg (d) metric ton Ans :- (b) quintal Explanation :- The unit of measurement ...
Brick walls are measured in square meter if the thickness of the wall is
(a) 10cm (b) 15cm (c) 20cm (d) None of these Ans :- (a) 10cm Explanation :- When brick masonry is ...
The unit of payment for the earthwork for embankment is
(a) per metre (b) per m3 (c) per number (d) per m3 Ans :- (d) per m3 Explanation :- The ...
The damp proof course (D.P.C.) is measured in
OR The quantity cement concrete damp-proofing course is measured in terms of (a) Cub.m (b) Sqm (c) Metres (d) None ...